Progress with Anson Rd Development

We’re now making good solid progress and we will have new tenants for the two flats in the main house by the middle of November. It’s taking longer to complete the eight flats in the new annex but we think we can see an end in sight with these flats being ready in mid-December. The new laundry should be ready around this time too.

 

We are also now looking at beginning the second phase of the development over the road at Carleton Road early in January 2015. This involves the building of two new flats at the rear of our property and the reconversion of the two ground floor flats in the main house – one of which has been used as the laundry